Riverwalk Project Area

Phase 1A


Status


Complete

The ribbon-cutting ceremony for Phase 1A of Riverwalk Park was held on April 11, 2016.

Location


Phase 1A, is located at the north end of the park, just north of the existing Chamber of Commerce.

Cost


Contractor: AG Pifer Construction Co., Inc.
Cost of Phase 1A: $1,048,664
Design and construction funded in part by $237,027 grant funding received from the Florida Inland Navigation District (FIND)
Riverwalk Ribbon-Cutting Ceremony
Riverwalk Building

Amenities


The amenities included in Phase 1A are:
  •  Kayak / canoe / stand up paddleboard launch
  •  New timber boardwalk and refurbishment of the existing timber fishing pier
  • 12 foot wide trail including a trailhead / concession stand / restroom facility
  • Crossover bridge to connect the new amenities to the existing Chamber of Commerce building
  • New lighting, landscaping and irrigation

Phase 1B


Status


Under construction
Completion date: November 2017

Cost


Contractor: Saboungi Construction, Inc.
Cost: $3,546,537
Design and construction to be funded in part by $350,000 grant funding from the Florida Inland Navigation District (FIND) and $400,000 from Volusia County ECHO
Riverwalk Park Phase 1B Map

Amenities


The amenities included in Phase 1B are:
  • Continuation of the 12'-wide trail way
  • Event lawn
  • Irrigation
  • Landscaping
  • Lighting
  • Multiple parking areas
  • Pavilions
  • Playground
  • Restroom/concession building
  • Seawall repair
  • Splash park
  • Storm water improvements